What is the Cone of Uncertainty in Scrum?

Home  »  Blog  »  What is the Cone of Uncertainty in Scrum? Cone of Uncertainty

Introduction:

One of the most frequent questions stakeholders ask in any project is: When can you finish the project? How much will it cost? What can we deliver in the next few months? These questions are important when beginning a business, but in the complicated world of software development, the answers are rarely clear. In this case, the concept of the Cone of Uncertainty becomes useful.

This cone of uncertainty is a predictive model approach that displays how close our estimates about projects can be at different points. At the initial stage, the estimations are large and wide with a lot of uncertainties, but as work moves on further into the next phases, the range of possible outcomes starts to narrow. This illustration gives teams and stakeholders more confidence in their predictions. In this article, we explore the Cone of Uncertainty in Scrum elaborately.

Picture1

The Cone of Uncertainty in Traditional Project Management

In traditional project management, the Cone of Uncertainty was used to show that cost, effort, and schedule estimates, which are generally very bad early in a project, but later stages continuously improve as the project moves through clearly defined stages like requirements gathering, analysis, design, coding, testing, and release.

This assumption was that once a phase was complete, nothing would ever be changed. For example, once requirements were finalized, no additional requirements could be accepted. This approach was founded on the idea that certainty would just keep increasing as the project progressed further..

But this “requirements freeze” method doesn’t work in software. We will be building features that our customers won’t use if we freeze requirements too soon. MS Word’s “Mail Merge” feature is a good example, built with effort but never used these days. Completing phases doesn’t guarantee higher certainty since business needs and user behavior keep changing.

The Role of Scrum Master and Product Owner

Both the Product Owner and Scrum Master are key figures in uncertainty management. The Scrum Master trains the team and stakeholders that uncertainty is a normal state and gets better through the process of inspection and adaptation. That is the main reason why many professionals nowadays focus on Scrum Master Certification, as it skills up Scrum masters with the necessary expertise to lead the teams through situations like estimation and delivery planning.

The Product Owner makes sure that backlog refinement is scheduled and that priorities are clear. With the right Product Ownership training, a Product Owner learns how to manage stakeholder expectations, oscillate business needs, and efficiently work on backlog items, all of which lead to a decrease in uncertainty. They, as a team, guide the Scrum Team through the narrowing cone and make the delivery flow predictable.

Scrum and the Cone of Uncertainty

The agile framework, Scrum, comes with completely different methods. Scrum uses empiricism (the principle that guides decision-making based on experience and observation) instead of phases so that teams can freely experiment, adjust, and deliver.  Every Sprint produces a potentially releasable Increment, and that Increment gives tangible evidence of progress.

For example, suppose there is a team of 500 units of work. They estimate they will finish within ten sprints, at a rate of 50 units per sprint.  That is only a theoretical guess before the first Sprint.  The team delivers ten units after the 1st Sprint.  They deliver 40 units after the 2nd Sprint.  These outcomes offer actual data. The team can now more accurately forecast, such as they would indicate that they would be capable of producing 30-90 units in the 3rd Sprint or that 150 units are possible within 5-15 Sprints.

Picture2

The uncertainty range is large at first, but it becomes smaller as the team identifies it produces more Sprints. The Cone gets smaller with time, and estimates are better. This is how Scrum’s Cone of Uncertainty gets realized; it is aided by facts from real increments and not by guesswork.

How the Cone of Uncertainty Functions

The product backlog is created at the start of every Scrum project, but is not well defined yet. It is hard to make truly clear estimates of time or cost when the team knows only high-level requirements. This is the reason why the initial phases are the most uncertain points.

The Scrum team continues to refine technical knowledge, adds acceptance criteria, and refines backlog items as they progress through iterations or Sprints. Such information shrinks the gap between starting hypotheses and end results. That is, the “cone” gets smaller with the passage of the project.

A feature can take two to eight weeks, say, but after some number of sprints, the team can reduce that estimate to a much tighter scope, three to four weeks, say. Stakeholders will be better able to grasp the Cone of Uncertainty, which is why initial estimates frequently are not accurate and why there must be patience as more data comes in.

Why is the Cone of Uncertainty Important in Scrum

When applying and working with Scrum, decisions are taken based on transparency, inspection, and adaptation. This Cone of Uncertainty is perfectly suitable for the Agile mindset, because it reminds teams and stakeholders about that:

  • Early estimates are not commitments. They are tentative and based on incomplete data and will certainly evolve.
  • Continuous feedback reduces risk. Each Sprint Review provides a chance to learn and adjust expectations.
  • Working together builds clarity. When Product Owners, Scrum Masters, and Development Teams work closely together, they identify hidden complexities more easily and quickly.

This practice prevents frustration and promotes trust between stakeholders and the team.

Practical Tips for Teams

Agile teams bring success when they follow the below simple but powerful habits in their day-to-day work, which help maintain clarity, adaptability, and stakeholder trust.

  • Refine Backlog Continuously: Periodic grooming sessions clarify requirements and enable the team to generate better estimates.
  • Use Relative Estimation: Story points and methods such as Planning Poker eschew false accuracy and support flexibility.
  • Send Feedback Frequently: Stakeholders must be regularly informed about the changing estimates.
  • Inspect and Adjust: Every Sprint is an opportunity for better understanding and adjusting the scope, timelines, or priorities.
  • Accept Uncertainty as Normal: Instead of worrying and raising disparity with Uncertainty, teams need to accept uncertainty as normal in the Agile process.

Conclusion:

The Cone of Uncertainty is not a problem to eliminate but a reality to manage. It shows that estimates improve with progress and learning. In Scrum, this improvement happens through Sprints, increments, and continuous feedback. 

By understanding and applying the Cone of Uncertainty, teams can avoid false certainty, make better decisions, and deliver real value. At last, Scrum proves that clarity grows not by freezing requirements but by learning through evidence, one Sprint at a time.